The Northern Review
51 (2021): 131–154 https://doi.org/10.22584/nr51.2021.008
Research Article
The Gahcho Kué Diamond Mine: A Case Study in Intergovernmental Environmental Management
Abstract: The Gahcho Kué Diamond Mine is an operating mine in the Northwest
Territories, Canada. Due to requirements defined in law, the mine required
several authorizations for construction and operation, including both federal
and territorial authorizations. Throughout the construction and operation of the
diamond mine, instances occurred when the proponent, De Beers Canada Inc.,
raised objections about applying conditions in the water licence
to areas that were authorized by Fisheries and Oceans Canada. As well, there
have been ongoing discussions between various parties, including those with
regulatory mandates, regarding requirements and jurisdiction related to site
closure planning. This article outlines the discussions that have occurred to
date, detailing the areas of ambiguity regarding projects that are authorized
under multiple pieces of legislation. Lessons learned, as well as
recommendations to address some of these issues, are provided.
1.0
Introduction
In
the realm of resource development, various environmental authorizations and
approvals are typically required from governments prior to a proponent
commencing a project. These may include, but are not limited to, environmental
assessments, water-based authorizations issued through provincial/territorial
legislation, and federal authorizations. Provincial and territorial governments
play an important role related to water legislation and policies in resource
development, and most water-related activities in Canada are seen as the
responsibility of these jurisdictions.1
In many cases, however, authorizations are issued under multiple pieces of
legislation, involve various levels of government, and can encompass unique
multi-jurisdictional approvals and approaches.
The
transition from environmental assessment during the project approval stage, to
specific operational authorizations at the permitting and licensing stage, can
be fairly linear and well understood. However, there
may be uncertainties and inconsistencies during various stages of the
development (e.g., construction, operations, and closure) with respect to
determining when various authorizations apply (e.g., between
territorial/provincial water-based authorizations and federal authorizations).
In
addition, settled land claims in the three territories of Canada (Yukon,
Northwest Territories, and Nunavut) have established environmental assessment
regimes that are unique and set them apart from other regions of Canada. As a
result, harmonizing these processes with the federal requirements is required.
This
article reviews the authorization process of a resource development project in
the Northwest Territories, Canada—the Gahcho Kué Diamond Mine—and studies the application of territorial
and federal legislation to the mine. The article outlines where there are clear
separations between jurisdictions, as well as highlights potential
uncertainties, or areas of overlap, that have occurred thus far in the project.
An overview of the discussions and decisions that have occurred to date related
to the project’s authorization process is provided. Finally, the article
includes lessons learned, as well as recommendations for achieving resolution
of the regulatory issues.
2.0
Background
De
Beers Canada Inc. (De Beers) has been operating the Gahcho
Kué Diamond Mine in the Northwest Territories,
Canada, since 2016. The mine is located approximately 280 km northeast of
Yellowknife at Kennady Lake (figure 1). The
kimberlite pipes, the ore bodies where the diamonds are found, are located
under the lake, and this required the construction and development of three
open pits known as Hearne, 5034, and Tuzo.2 To enable safe access to the kimberlite pipes, De Beers
had to isolate, fish out, and dewater Kennady Lake.
Figure 1. Location of the Gahcho Kué Diamond Mine,
Northwest Territories, Canada. (Government of Northwest Territories).
2.1
Authorization under the Federal Fisheries Act
The
dewatering of Kennady Lake resulted in the removal of
over 18,000 fish3 and the loss
of over 670 hectares of fish habitat,4
which required approvals from Fisheries and Oceans Canada (DFO) under a Fisheries Act authorization issued June 30, 2014.
Of note, the fish removed from Kennady Lake were
given to local communities and members of impacted Indigenous governments and
organizations, such as the Yellowknives Dene First
Nation, at their request.
The
Fisheries Act authorization was a
requirement under section 35 of the Fisheries Act,5 which at that time prohibited
the “serious harm” of fish unless authorized. Serious harm was defined in the
Act as “the death of fish or any permanent alteration to, or destruction of,
fish habitat.”6 As such,
given the permanent alteration of habitat and death of fish, De Beers needed to
obtain an authorization under the Act before they could proceed with draining Kennady Lake.
The
process of isolating and fishing out a lake to allow access to diamond ore
bodies is a process previously approved in the Northwest Territories (NWT) on a
site-specific basis, and is guided by the “General Fish-out Protocol for Lakes
and Impoundments in the Northwest Territories and Nunavut.”7 This protocol provides general
guidance for proponents that have been authorized to remove all fish from a
lake; however similar to most guidance documents, it tends to avoid being
prescriptive to allow the proponent to work with affected parties to determine
specific details, such as potentially salvaging fish when possible. There are
different ways that these fish are destroyed and managed (e.g., relocation),
which may have been preferred by the Indigenous stakeholders (see section 2.5),
and to ensure fish are provided to communities to avoid wastage—the latter is a
requirement of condition 2.2 of De Beers’s Fisheries Act authorization.
2.2
Environmental Assessment and Environmental Impact Review under the Federal Mackenzie Valley Resource Management Act (MVRMA)
In
addition to the requirements outlined under the federal Fisheries Act authorization, projects in the
Mackenzie Valley, Northwest Territories, fall within the environmental
assessment regime of the federal Mackenzie Valley
Resource Management Act (MVRMA)8 (figure 2). The MVRMA9 came into force in 1998 and was enacted as a result of
the negotiation of comprehensive land claim agreements in the Northwest
Territories, differentiating it from other provincial and federal resource
management legislation. The Mackenzie Valley
Resource Management Act provides for the creation of quasi-judicial
co-management boards, which are established to carry out various activities
such as land use planning (land use planning boards) and land and water
regulation (land and water boards). Specifically, Part 3 of the MVRMA allows a
land and water board to issue land use permits and water licences
required under any territorial law within its jurisdiction, including the
territorial Waters Act.10 Of note, subsection 27(5) of
the Waters Act allows for land and
water boards to set standards and conditions that are more protective than
other requirements. As well, Part 5 of the MVRMA outlines the requirements for a
preliminary screening of proposed projects and a process whereby projects can
be referred to an environmental assessment (EA) conducted by the Mackenzie
Valley Environmental Impact Review Board (the review board) or a more
comprehensive environmental impact review (EIR) conducted by a review panel.11 The MVRMA also outlines the
role of the various federal and territorial departments related to Part 5.
Various stakeholders, including the review board and all federal and territorial
departments, have referral authority under the MVRMA, which allows them to
refer a development to environmental assessment or environmental impact review.
Figure 2.
Mackenzie Valley, Northwest Territories, Canada. (Government of Northwest
Territories).
In
the case of the Gahcho Kué
Diamond Mine, De Beers applied to the Mackenzie Valley Land and Water Board
(MVLWB) for a Type A water licence on November 24,
2005, which was referred to environmental assessment by Environment Canada12 on December 22, 2005.
Pursuant to MVRMA section 128(1)(c), the review board subsequently ordered an
environmental impact review of the proposed development on June 12, 2006. The
Report of EIR13 was
released by the review board’s Gahcho Kué Panel on July 19, 2013,14 and the project was subsequently approved by the
Minister of Aboriginal Affairs and Northern Development Canada.15
2.3 Water Licensing under the Waters Act
Following
the environmental impact review decision, the water licensing process proceeded
under the territorial Waters Act.16 A
Type A water licence was issued in September 2014 by
the MVLWB following approval by the Minister of Government of Northwest
Territories – Department of Environment and Natural Resources (GNWT-ENR).17 The water licence
included conditions requiring the submission of various management plans prior
to and during construction and operations such as a water management plan and
dyke construction plans. Further, the requirements for various iterations of
closure and reclamation plans (interim versions and then a final version
required two years before the end of mine life) are included in the water licence.
2.4 Government of Northwest Territories Role in Territorial Regulatory
Processes
The
land and water boards (LWBs) established under the federal Mackenzie Valley Resource Management Act
have requirements to distribute water licence and
land use permit applications and associated plans for public comment.
Applications are distributed to federal and territorial government departments,
Indigenous governments and organizations, and local community governments
amongst others. All comments received, as well as responses from the proponent,
are published and available through an online public registry maintained by
relevant LWBs. Through this process, Northwest Territories government
departments, including the Department of Environment and Natural Resources,
provide advice on project-related submissions, such as those outlined above
from De Beers. As well, monitoring and enforcing the conditions of water licences issued on territorial and private lands in the
Mackenzie Valley is conducted by GNWT inspectors. Finally, the territorial
government is liable for these lands where licensed and permitted activities
occur, and retains securities posted by the proponents to cover such
liabilities should the proponent become insolvent.
2.5 Consultation and Engagement
Section
35 of the Canadian Constitution Act, 1982,
recognizes and affirms the existing Aboriginal and treaty rights of Indigenous
Peoples, and these can be affected by freshwater management decisions. Further,
as noted above, there are comprehensive requirements under the federal MVRMA
related to engagement with potentially impacted Indigenous governments and
organizations, and the processes provide opportunities for technical sessions
and public hearings for stakeholders to participate.
For
example, during the environmental impact review, public hearings were held in
the communities of Dettah, Lutsel
K’e, and Yellowknife. Of particular note, through the
recommendation of several Indigenous stakeholders during
the EIR, Ni Hadi Xa18 was developed, an organization responsible for
monitoring the mine site. This organization consisted of six Indigenous Nations
(Deninu Kue First Nation, Lutsel K’e Dene First Nation,
North Slave Métis Alliance, Northwest Territory Métis Nation, Tłı̨chǫ Government, and Yellowknives
Dene First Nation), as well as De Beers. During the water licensing process,
participation included Ni Hadi Xa,
Tłı̨chǫ Government, North Slave Metis Alliance, and Akaitcho Interim Measures Agreement Implementation Office.
As well, within the Fisheries Act
authorization, there were references to required discussions with the same
parties that comprise Ni Hadi Xa,
on research projects related to offsetting requirements.
Finally,
it should be mentioned that De Beers and the co-management boards conducted
quite an abundance of engagement sessions throughout the approval process of
the mine, and these continue to be ongoing through operations including
discussion about monitoring results, closure planning, and mine plan updates.
Given the scope of this article, it is not possible to provide a detailed or
in-depth review of Crown consultation and proponent engagement, nor the
contributions of various parties to these processes; an outline is provided as
part of the general overview of mine approval process in the Northwest
Territories.
3.0 Intergovernmental Environmental Management at the Gahcho
Kué Diamond Mine
3.1
Construction and Operations
During
the construction and operation of the Gahcho Kué Diamond Mine, there have been several instances when De
Beers has outlined uncertainty as to whether specific matters pertained to the
water licence issued by the MVLWB, or whether they
were covered within the scope of the Fisheries Act
authorization. Specifically, De Beers has challenged comments from GNWT-ENR and
the MVLWB in instances where De Beers believes the Fisheries
Act authorization allows specific activities that are not regulated by,
or outside the scope of, the water licence.
As
outlined in section 2 above, Fisheries and Oceans Canada issued the Fisheries Act authorization to De Beers for
dewatering Kennady Lake in order to
provide safe access to the diamond ore bodies and construction of the open
pits. In addition to the Fisheries Act authorization,
the water licence issued under the territorial Waters Act includes conditions related to
the requirement of plans19
and effluent quality criteria (EQC),20
among others.
3.1.1 Dyke A Construction
An
early example of jurisdictional uncertainty occurred during the initial dyke construction in Kennady Lake,
which was required in order to isolate the water management pond from the
downstream environment. Post-construction, the majority of
Kennady Lake was to be used by De Beers as a water
management pond to store wastewater until such time that the water could be
discharged into the receiving environment. The creation of the water management
pond required the construction of several dykes to
isolate the areas, the removal of fish from the lake, and dewatering the lake.
The water licence, and management plans required
under the water licence, included requirements for
implementing mitigation measures at the mine site and in the aquatic
environment during dyke construction. Mitigation
included isolating the open-water environment and downstream-receiving
environment during construction (i.e., turbidity barriers), and establishing
effluent quality criteria (EQC) for total suspended solids (TSS) in water being
discharged from the area.
Of
note, Kennady Lake was divided into eight areas,
named Areas 1–8, to assist in construction planning and aid in construction
sequencing (figure 3).21
The eastern portion of Kennady Lake, Area 8, was to
remain connected to the downstream environment. Areas 1–7 were within the
footprint of the future water management pond and were to be fished out and
dewatered at various times throughout the sequencing of project construction.
One of the initial construction requirements was the construction of Dyke A, which was to be placed between Area 7 (within the
footprint of the future water management pond) and Area 8 (the receiving
environment).
Figure 3. Water Management Area in Kennady Lake. (Source: De Beers, Gahcho Kué
Operational Management Water Plan, Version 6.1, Figure 2, June 2021, http://registry.mvlwb.ca/Documents/MV2005L2-0015/MV2005L2-0015%20-%20De%20Beers%20Gahcho%20Kue%20-%20Operational%20Water%20Management%20Plan%20V6.2%20-%20June%208_21.pdf)
In
2014, management plans related to the construction of Dyke A were circulated
for review as per the aforementioned process required
under the Mackenzie Valley Resource Management
Act. De Beers noted, within the “Dyke A Construction and Monitoring
Plan Version 2,”22 that
turbidity barriers would be placed on both sides of the dyke being constructed,
but TSS limits would only apply to water discharged from Area 7 into Area 8.
The only EQC criterion related to Area 7 was that if TSS concentrations were
above approved limits within the area, discharge into Area 8 would cease. De
Beers noted that the rationale for this was that impacts would be reduced in
Area 7 at the time of dyke construction as the area would be fished out.23 Although Dyke A was
constructed in 2014, while Phase 1 of the fish out was completed in the summer
of 2014, the fish out in its entirety was not completed until later in 2015.24 Given that the fish out had
not been completed within Area 7 at the time of Dyke A construction, and since
fish still remained within the footprint of the water management pond (Area 7),
the Department of Environment and Natural Resources noted that impacts to the
open-water aquatic environment should be regulated.25 GNWT-ENR also indicated
that the area should not be considered a “Water Management Pond” until the area
had been isolated, fished out, and dewatered, and that fish may still be
present within the area.26
With respect to the Fisheries Act and Fisheries Act authorization, it was also unclear at
which point the water management pond would be considered authorized, or when
the general pollution prevention prohibitions under section 36 of that Act
would no longer apply.27
In response, De Beers noted that they had “been issued a Fisheries Act
Authorization by Fisheries and Oceans Canada and have consulted with them on
the construction activities,”28
with the implication that activities occurring related to Dyke A construction
were within the jurisdiction of the Fisheries Act authorization
and that they were not required to respond to specific concerns from the
territorial Department of Environment and Natural Resources.
The
outstanding question in this case was at what point does the Fisheries Act authorization for the future
conversion of Area 7 of Kennady Lake into a section
of the water management pond limit the authority of parties under the
territorial Waters Act and conditions
of the water licence (e.g., TSS limits in Area
7/water management pond) for fish still remaining in that area.
Regarding
the query from GNWT-ENR and the response from De Beers, the Mackenzie Valley
Land and Water Board made the following determination:
Board
staff recognizes that this may create a short term
impact on water quality in Area 7, however, this area will be completely drawn
down and will not constitute aquatic habitat during the operational phase of
the project. Board staff is of the understanding that these fish are going to
be removed but not be relocated to another area.29
It
appears that the board’s ruling suggests that while they were aware of
short-term impacts to any aquatic species that had not yet been removed from
Area 7 of Kennady Lake, this was considered a low
risk given that the fish would be eventually removed but not relocated to
another area (i.e., destroyed).
3.1.2
Additional Dyke Construction
The
following year (2015) another plan approval was required under the water licence, for the construction of additional dykes in Kennady Lake. Again,
GNWT-ENR outlined concerns that increased levels of total suspended solids were
being permitted within the future footprint of the water management pond while
fish still remained in those areas.30
GNWT-ENR also noted that throughout the plan it appeared that De Beers was
suggesting a higher level of TSS would be permitted within Kennady
Lake during construction since “internal” dykes were isolating the downstream
environment via the previously constructed Dyke A. As such, the GNWT-ENR
requested that De Beers clarify the phase and status of the fish out of Kennady Lake to understand if any fish species were still
within the lake.31 In May
2015, De Beers provided information indicating that the fish out was being
completed in phases—Phase 1 in the summer of 2014, Phase 2 in July 2015, and
Phase 3 potentially to be completed in August 2015.32 De Beers also noted that turbidity barriers would be
located on both sides of the dyke, similar to those installed during the
construction of Dyke A in 2014. While monitoring was being conducted within the
areas during fish out, several monitoring stations were to be sampled “only if
discharge from Area 7 to Area 8 is planned to occur,”33 again indicating that areas
within the interior of Kennady Lake that still retained
fish at that point would be less protected.34
3.2 Closure Planning
There
has also been significant discussion between De Beers, GNWT-ENR, and the
Mackenzie Valley Land and Water Board related to closure planning of the site.
The land and water boards require mining projects to develop closure and
reclamation plans guided by the “Guidelines for the Closure and Reclamation of
Advanced Mineral Exploration Sites and Mine Sites in the Northwest Territories.”35
Through these processes, the board and other parties, including the GNWT-ENR,
have been incorporating fisheries aspects into long-term closure planning of
the site. During project approvals (e.g., environmental impact review), it was
understood that, post-closure, the majority of Kennady
Lake would return to a functioning aquatic ecosystem with fisheries populations
similar to baseline conditions.36
According to the most recent mine plan, the
mine is now anticipated to be operational for fourteen years (ending in 2030)
with a closure period that includes at least a twenty-year timeline for lake
refilling.37
De
Beers has indicated concern throughout this closure planning process that there
may be duplication of closure efforts to accommodate stakeholders’ issues
related to fisheries components of the project. They have indicated their
position that, under the Fisheries Act authorization,
DFO is the primary regulator for fisheries aspects and monitoring the return of
fish to Kennady Lake and that, therefore,
fishery-related requirements are outside the scope of the land and water
board’s authority38 and
may not be relevant to the closure and reclamation plan required under the
water licence. For example, during the review of the
interim closure and reclamation plan (ICRP) version 4 in 2018, there was a
discussion on the monitoring requirements for the establishment of fish
communities post-closure.39
GNWT-ENR, as well as Environment and Climate Change Canada, outlined concerns
that the two years of fisheries monitoring proposed by De Beers was
insufficient to determine the return of a stable, functioning aquatic ecosystem
over the long-term in Kennady Lake.40 De Beers’s
proposed fisheries monitoring was related to requirements under the Fisheries Act authorization, which state:
The
use of the fish habitat features within Kennady Lake
shall be evaluated by demonstrating fish presence on the features at the
appropriate life stages, as defined in the Fish Habitat Validation Plan which
will be submitted to DFO for approval prior to final construction of the fish
habitat features. Once this has been confirmed in
two successive years this monitoring may be discontinued.41 (emphasis added)
GNWT-ENR’s
concern was that these requirements are related to specific fish habitat
features, and not whole lake fish population recovery, as a closure objective.42 GNWT-ENR also referenced a
comment from De Beers’s environmental impact
statement,43 which
summarized the length of time that was required for fisheries populations to
return to Kennady Lake. De Beers noted that based on
the slower recovery times of Arctic systems as a result of colder temperatures,
shorter growing seasons, and low nutrient availability, full recovery of the
system would likely take between fifty and sixty years following the complete
refilling of Kennady Lake, or between sixty and
seventy-six years following the end of operations. Specifically, De Beers noted
that a self-sustaining northern pike population would take approximately fifty
to sixty years to re-establish in Kennady Lake and
that the return time of the previous dominant piscivore, lake trout, would
likely take sixty to seventy-six years to establish a self-sustaining
population following the complete refilling of the lake.44
As
such, GNWT-ENR suggested that the monitoring requirements included in the Fisheries Act authorization were likely
insufficient during the post-closure period, in order to ensure that the
aquatic environment is re-established, and the department suggested several
rounds of post-closure monitoring, at three-year intervals, to monitor the
recovery of fish populations within the lake.45
In
their response, De Beers reiterated their disagreement with GNWT-ENR and
maintained the position that Fisheries and Oceans Canada (DFO) is the lead
regulatory agency of fish and fish habitat and the Fisheries
Act is sufficient.46
Furthermore, De Beers noted it is DFO’s responsibility to determine success
with respect to establishment of fish habitat, not the GNWT-ENR or the
Mackenzie Valley Land and Water Board. De Beers concluded that “it is not
necessary or appropriate for the MVLWB to also regulate this through redundant
or close to redundant monitoring or reporting mechanisms.”47
In
their subsequent decision to not approve De Beers’s
interim closure and reclamation plan (ICRP) version 4 for the mine, the MVLWB
outlined that ecosystem recovery success should include proof of long-term
sustainability.48 The
MVLWB continued that closure objectives related to Kennady
Lake and the open pits were broader than the Fisheries
Act authorization, and that meeting the requirements of the Fisheries Act authorization were only one
criterion. The objectives are noted as returning “Kennady Lake to a state that will support a functioning
aquatic ecosystem and traditional uses” and “that the backfilled and/or flooded
pits will not adversely impact establishment and maintenance of sustainable
aquatic ecosystems in the overlying Kennady Lake and
downstream waterbodies.”49
Furthermore,
MVLWB noted that the goal defined for closure of the mine site remained
returning the site to a “viable, and wherever practicable, self-sustaining
ecosystem that is compatible with a healthy environment, human activities, and
the surrounding environment.”50
It was concluded by the MVLWB that the Fisheries Act
authorization does “not release De Beers from any obligations to obtain
permission from or to comply with the requirements of any other regulatory
agencies.”51 The MVLWB
provided specific examples of instances when this logic was presented (see
section 4), to support the position that the MVLWB can address, generally, the
issue of fish habitat in discussions on closure and reclamation. Regarding the
redundancies noted by De Beers, the MVLWB responded that concerns raised by
GNWT-ENR were justified. The MVLWB concluded that monitoring in addition to Fisheries Act authorization requirements, and the
acceptance of a performance assessment, would be required to ensure closure
objectives are met.52
4.0 Legal Precedents Related to Intergovernmental Environmental Management in
NWT
As
noted in section 3.2 of this article, when making its decision on the fisheries
jurisdiction related to closure at the Gahcho Kué Diamond Mine, the MVLWB referenced previous discussions
that occurred through the process of another land and water board in the
Mackenzie Valley—the Wek’èezhii Land and Water Board
(WLWB) related to the Ekati Diamond Mine and then
operator BHP Billiton Diamonds Inc. (BHP).
During
the development and review period related to an Interim Closure and Reclamation
Plan in 2009, BHP submitted a motion to the land and water board requesting a
ruling on the board’s jurisdiction over fish habitat. Specifically, the cover
letter of the ruling requested clarification on:
Whether
the Wek’èezhìi Land and Water Board, in the context
of BHP Billiton Diamond Inc.’s obligations relating to closure and reclamation
of the EKATI Diamond Mine, has the jurisdiction to require that BHP Billiton
Diamond Inc. establish and maintain fish or fish habitat in the closed pit
lakes or the Long Lake Containment Facility at the EKATI Diamond Mine.53
BHP
noted that the issues raised during discussions between interested parties,
including Indigenous governments and organizations, which had been occurring
throughout the closure planning process, focused on the establishment of fish
habitat in the closed-pit lakes and the Long Lake Containment Facility.54 BHP’s position was that they
had entered into a previous agreement with DFO in 1996, which provided “full and final compensation for the permanent loss
of fish habitat for the life of the project.”55 Specifically, BHP had been authorized under the Fisheries Act to destroy fish habitat with
the condition to pay monetary compensation of $1.5 million to DFO, which was to
be directed towards fish habitat restoration and enhancement projects off-site.56 Subsequently, the board ruled
on the request from BHP and concluded “BHP
Billiton has not convinced the WLWB that its jurisdiction is limited or even
affected in any way by the 1996 agreement. Therefore the WLWB rules that it
does have the authority to require BHP Billiton to create fish habitat in the
exercise of its reclamation authority.”57
The WLWB further stated that the existing agreement between BHP and DFO “does
not in any way limit the exercise of its jurisdiction to require the
re-establishment of fish habitat as part of the Interim Closure and Reclamation
Plan for the EKATI site.”58
BHP
Billiton then proceeded to appeal the ruling to the Supreme Court of the
Northwest Territories.59
The application was dismissed as the court ruled that it was premature to
determine if the closure plan conflicted with any agreements and requirements
stipulated by DFO as the board had yet not made any decisions related to the
interim closure and reclamation plan. Specifically,
(t)he
Superior Court held that the Board had authority to make decisions with respect
to reclamation in the mined area. BHP had an obligation to make a reclamation
plan. It was premature to seek review of the Board’s decision on BHP’s
reclamation plan where it was not yet clear whether or not the decision would
conflict with BHP’s agreement with the Federal government.60
As
such, given the status of BHP Billiton’s closure plan and the uncertainty of
how final closure options may overlap with previous agreements between BHP
Billiton and DFO, it was premature for the Court to review the board’s decision
so this case did not lead to a judicial decision that may have set a precedent
for jurisdictional matters related to fish habitat at that time.
While
the Ekati mine proceeding highlights that some
uncertainty still remains regarding closure jurisdiction between DFO and the
land and water boards of the Mackenzie Valley, there have been no related discussions
about jurisdiction during construction and operations, similar to the issues
outlined in section 3.1, of the Gahcho Kué Diamond Mine. As well, it should be noted that the
closure discussions relevant to Ekati were not
specifically “that the Board did not have jurisdiction to deal with reclamation
of fish habitat generally, but that, in light of the 1996 compensation
agreement, its jurisdiction to do so with respect to the EKATI project was
displaced.”61 As such, at
this point there have been no formal decisions or discussions made in the NWT
regarding land and water board jurisdiction that could be relevant to the
site-specific discussions and activities that have occurred at the Gahcho Kué Diamond Mine.
5.0 Discussion
There
remains some uncertainty in how federal and territorial legislation apply to
resource development projects in the Northwest Territories. Regarding the
construction and operational considerations during dyke
constructions within Kennady Lake, there have been
valuable discussions between De Beers, the Mackenzie Valley Land and Water
Board, and the Government of Northwest Territories Department of Environment
and Natural Resources. De Beers has raised several concerns during this period
including questioning why criteria related to a territorial water licence would be required for discharge to an area that was
already authorized for destruction under federal legislation. The question from
the GNWT-ENR can be summarized by a single point: at which point does an open
water environment (i.e., the existing Kennady Lake
Areas 1-7) become authorized for destruction under a Fisheries Act authorization (i.e., water management
pond). Although this area had been authorized, fish still
remained in the lake when in-lake dyke construction began in 2014. It
may have been beneficial for parties to conduct a start-up meeting after De
Beers initially received its authorizations, in order to
provide those involved with an understanding related to jurisdictions and the
sequencing of events.
GNWT-ENR’s
opinion was that, during the construction phase, and until a fish-out was
completed, the requirements under the Waters Act
and the associated water licence should be adhered
to.62 Although the MVLWB
may have been justified in their response that the water quality issues may be
a moot point since fish within Kennady Lake were to
be removed, as noted in section 2, there are different ways that these fish
could have been managed (e.g., captured by gill nets during a fish out vs
incidental death during dyke construction) that may have been preferred by the
affected Indigenous organizations and governments noted previously.
There
also seems to be more certainty required in understanding intergovernmental
environmental management roles related to closure planning. While most northern
regulators consider BHP Billiton Diamonds Inc. v.
Wek’èezhii Land and Water Board to outline
the northern regulatory board’s jurisdiction related to fish habitat at
closure, –that case is different in that it was specific to how previous
compensation under the Fisheries Act would
be considered in relation to add–itional requirements
from regulatory boards, and the case was dismissed given the preliminary nature
of the legal challenge in regard to the Board’s review and decision process. Of
importance, it was discussed throughout that process that BHP had not
challenged the board’s jurisdiction over fish habitat at closure in general
terms, but that they argued compensation had already been paid to DFO.
In
the case of the Gahcho Kué
Diamond Mine, De Beers’s position is more general in
that the MVLWB and the GNWT-ENR have no authority regarding the recommendations
about the period of closure monitoring related to the successful re-establishment
of the aquatic environment within Kennady Lake.63 In this instance, the board’s
position was that the monitoring was required to determine that objectives
under the water licence’s closure planning requirements
were met, and as such the MVLWB and the GNWT-ENR were justified in their
positions on the matter.64
It may be beneficial for federal and territorial regulators to consider more
formal policy or legislative updates outlining how aspects of fisheries
protection are covered under relevant federal and territorial legislation.
As
with all jurisdictional matters and overlapping mandates, some debate will likely continue until a case
advances to an appeal court. Regarding natural resources exploitation, in an
analysis of Canadian watershed management, Hill et al. noted that, to avoid
conflict, legislation tends to provide allowances for these activities.65 Where there has been
conflict, it has been observed that courts tend to rely heavily on the
expertise of environmental boards and that a considerable amount of deference
is given to these boards.66
The judge specifically noted in BHP Billiton
Diamonds Inc. v. Wek’èezhii Land and Water Board that
“(g)enerally speaking, courts are extremely reluctant
to intervene in ongoing administrative proceedings and subject interlocutory
decisions of an administrative tribunal to judicial review.”67 Even if a decision is made,
the particulars of the case are often relatively specific and cannot
necessarily be applied carte blanche to other situations.
The
responsibility for water-related activities tends to be a
provincial/territorial matter and this level of management “includes the
ability to be responsive to citizen needs and environmental concerns.”68 In general, the law of
paramountcy applies whereby federal legislation takes precedence over
territorial legislation; but in many regulatory cases, the authorizations are
complementary to each other. As well, as discussed previously, the land and
water boards that issue water licences under the Waters Act are given their authority under
the federal Mackenzie Valley Resource Management
Act. As noted, the MVRMA is linked to the establishment of several
comprehensive land claims in the Northwest Territories, which adds a layer of
legal complexity. Regarding the specifics of this case study, the existing
territorial regulatory regime should provide additional clarity with respect to
jurisdiction as previous recommendations from water policy reviews suggested
the establishment of watershed agencies that would make “provision for all
aspects of water use” by “federal and provincial delegation of the necessary
powers to a jointly established system of agencies.”69
A
clear path forward would be best attained through the cooperation of regulatory
bodies in the Northwest Territories to provide direction to industry in this regard.
In the context of water policy between provinces and territories, Hill et al.
noted that the process of harmonization to achieve “regulatory efficiency,
effectiveness and clarity through standardization and centralization”70 would
be desirable to help achieve clarity between federal and provincial/territorial
jurisdiction.
During
the public inquiry into the E.coli contamination of the municipal water supply
in Walkerton, Ontario,71
it was recommended that a path forward involved additional intergovernmental
coordination “in an area where constitutional jurisdiction is not always
clear.”72 Other recommendations for jurisdictional clarity
that have been noted previously include the federal government engaging in
“research and guidance in terms of intersecting jurisdictional authority”73 and that “intergovernmental coordination
is necessary to address local government matters.”74 Discussions on these matters can be difficult but are
often valuable. As noted by Gormley, discussion on intergovernmental conflicts
should not be worrisome but allows for additional debate and clarity, which
should be celebrated.75 It
should be noted that in the context of this case study, the discussion has
originated from the proponents rather than the federal or territorial
government or the regulatory board. However, a coordinated response from the
relevant agencies could pre-emptively avoid additional debate in the future.
6.0 Conclusion
It
appears that the fisheries aspects discussed and included within the scope of
the water licence related to closure of the Gahcho Kué Diamond Mine fall
within the jurisdiction of the Northwest Territories Waters Act, and
should be discussed further by the Mackenzie Valley Land and Water Board, the
Government of the Northwest Territories Department of Environment and Natural
Resources, and other interested parties privy to those processes, including
Indigenous governments and organizations. There appears to be less clarity
related to initial open-water construction, which may require additional
discussion between parties. At this point, there is no resolution regarding
different authorizations to the same activities of a project. However, there
could be resolution provided if progress was made in areas discussed throughout
this article and outlined below in the recommendations.
Recommendations
to further the resolution of issues related to intergovernmental environmental
management include the following:
1. The Government of the Northwest Territories, the land and
water boards, and Fisheries and Oceans Canada should discuss sequencing of
authorizations to provide clear understanding to proponents in instances where
a Fisheries Act authorization excludes a
water body from the protection of water quality protection provisions of other
federal and territorial legislation.
2. In instances where both a water licence
and Fisheries Act authorization are required,
the land and water boards should clarify if any conditions of the water licence do not apply to any areas that are dually
authorized, and whether this applies throughout the duration of the project or
only during certain phases.
3. Prior to the commencement of major projects subject to
intergovernmental environmental management, the proponent and all regulators
should discuss the applicability of the various authorizations to ensure that
expectations are understood and areas of uncertainty
and potential overlap are identified.
Gibson
noted that “it is not surprising to find that both federal and provincial
governments have difficulty determining their respective fields of
responsibility” in the area of environmental
management and that “constitutions are necessarily written in general language,
and the application of that general language to situations that were not
contemplated when the constitution was written is a matter of speculation, at
least until ruled upon by the courts.” 76
As such, uncertainty often remains in these areas until additional decisions
are made by the courts.
In
closing, the challenge with intergovernmental environmental management is very
well articulated by Justice Vertes in the dismissal
of BHP Billiton Diamonds Inc. v. Wek’èezhii Land and Water Board, and he also
offers some clear steps forward:
In
my opinion these submissions make a self-evident point. In a complex regulatory
environment, where numerous pieces of legislation apply to the same project, it
is up to each regulatory body to try to avoid conflict in their decisions with
other bodies. Otherwise, the desired objective of having an integrated scheme
of resource management becomes unattainable.77
At
the time of this article’s publication, the Gahcho Kué Diamond Mine is in year five of fourteen of its
expected mine life, which may be extended based on ongoing evaluations of the
resource. As such, there will ongoing discussions between De Beers, federal and
territorial departments, and Indigenous governments and organizations, through
the remainder of operations and into closure, to determine the expectations of
all parties related to the long-term goals for Kennady
Lake. On a final note, the Metal and Diamond Mine Effluent Regulations
(formerly Metal Mine Effluent Regulations) were updated in June 2018. As
diamond mines are now included in these regulations, a tailings impoundment
area for a mine (i.e., Kennady Lake) could now be
scheduled, and the Fisheries Act prohibitions
regarding water quality would no longer apply, nor, potentially, would aspects
of the Waters Act. Alternatively,
there is a discussion ongoing between the federal government and Northwest
Territories territorial government to reach an “equivalency in effect”
agreement whereby section 36 of the Fisheries Act—prohibition
of deleterious substances into water frequented by fish—would not apply in the Northwest Territories and
would cede to equivalent territorial legislation. These ongoing discussions
will impact how any diamond or metal mining development in the future is managed.
Notes
1.
C. Hill, K.
Furlong, K. Bakker, and A. Cohen, “Harmonization Versus Subsidiarity in Water
Governance: A Review of Water Governance and Legislation in the Canadian
Provinces and Territories,” Canadian Water
Resources Journal 33,
no. 4: 315–332, https://doi.org/10.4296/cwrj3304315
2.
De Beers
Canada Inc., 2014 Annual Land and
Water Licence Report (March 2015).
3. De
Beers Canada Inc., Gahcho Kué Mine 2015
Fisheries Act Authorization Annual Report (December 2015).
4. Canada, Fisheries and Oceans Canada, Fisheries Act Authorization 03-HCAA-CA6-00057, issued to De Beers Canada Inc., June 30, 2014, http://registry.mvlwb.ca/Documents/MV2005L2-0015/MV2005L2-0015%20-%20De%20Beers%20Gahcho%20Kue%20-%20Fisheries%20Act%20Authorization%20-%20Jun30-14.pdf.
5.
Fisheries Act, RSC
1985, c F-14.
6.
“Serious harm”
was introduced in October
2013 during an amendment to the Fisheries Act
which replaced the previous habitat protection provisions of Section 35.
Additional amendments to the Act in 2019 saw the return of the habitat
protection provisions.
7.
J.D. Tyson,
W.M. Tonn, S.
Boss, and B.W. Hanna, “General Fish-Out Protocol for Lakes and Impoundments in
the Northwest Territories and Nunavut,” Canadian Technical Report of Fisheries and Aquatic Sciences
2935 (2011): 34, https://www.researchgate.net/publication/325697872_General_Fish-out_Protocol_for_Lakes_and_Impoundments_in_the_Northwest_Territories_and_Nunavut.
8.
The
Inuvialuit Settlement Region in northern
NWT remains within the jurisdiction of the Canadian Environmental Assessment Act
while the Mackenzie Valley areas fall within the jurisdiction of the Mackenzie
Valley Resource Management Act (MVRMA).
9.
Mackenzie
Valley Resource Management Act, SC 1998, c.
25, https://laws-lois.justice.gc.ca/PDF/M-0.2.pdf.
10.
Waters Act, SNWT
2014, c.18, https://www.justice.gov.nt.ca/en/files/legislation/waters/waters.a.pdf.
11.
An
Environmental Impact Review is a more
exhaustive review process allowable under the MVRMA and requires the
establishment of a panel. To date, only the Gahcho Kué Diamond Mine and the Mackenzie Gas Project have been
subject to an Environmental Impact Review.
12. Now
Environment and Climate
Change Canada.
13. Mackenzie Valley Environmental Impact Review Board Gahcho Kué Panel, Report of Environmental Impact Review and Reasons for Decision, EIR 0607-001, Gahcho Kué Diamond Mine Project (Yellowknife, NWT, July 19, 2013), https://reviewboard.ca/upload/project_document/EIR0607-001_Gahcho_Kue_Diamond_Mine_Project_Report_of_EIR.PDF
14.
Regarding the
time lag between the
commencement of the EIR and the final decision, while the EIR was ordered in
2006, the proponent requested a judicial review that was ongoing from
2006-2007. Additionally, the proponent requested an adjournment in 2008 that
was resumed in 2010.
15.
Now
Crown–Indigenous Relations and Northern
Affairs Canada
16.
The Waters Act is administered by
the Government of the Northwest Territories, Department of Environment and
Natural Resources.
17.
On April 1,
2014, the federal government
devolved certain land and water authorities to the GNWT. As such, the GNWT
Minister of Environment and Natural Resources approves Type “A” water licences as of that date under the territorial Waters Act prior to
issuance by the land and water boards. The Gahcho Kué Diamond Mine process was ongoing at this date and the licence issuance date occurred post-devolution by the GNWT.
18.
More
information can be found at https://nihadixa.ca/
19.
Plans are
required for activities such as dyke construction, water management during construction and
operation, monitoring plans, etc.
20. EQC
are limits of parameters in wastewater
that must be met prior to discharge from the site into the environment, or
limits that must be met in the receiving environment during construction.
21. De Beers Canada Inc., Dyke Construction Management Plan – Dykes B, D, E and Perimeter Berms (Version 2) (April 2017), http://registry.mvlwb.ca/Documents/MV2005L2-0015/MV2005C0032%20-%20De%20Beers%20Gahcho%20Kue%20-%20Dyke%20Construction%20Management%20Plan%20Dykes%20B,%20D,%20E,%20and%20Perimeter%20Berms%20(V.2)%20-%20Apr%2017_17.pdf.
22.
De Beers
Canada Inc., Dyke A
Construction and Management Plan, Version 2 (September 15, 2014).
23.
De Beers
Canada Inc., Dyke A Construction
and Management Plan, Version 2 (September 15, 2014).
24.
De Beers, Gahcho Kué
Mine Lue T’e
Halye, Fish-Out Annual Report 2015 (December 2015).
25.
Government of
the Northwest Territories,
Environment and Natural Resources, Letter from GNWT–ENR to MVLWB re Dyke A
Construction and Management Plan, October 9, 2014.
26.
Government of
the Northwest Territories,
Environment and Natural Resources, Letter from GNWT–ENR to MVLWB re Dyke A
Construction and Management Plan, October 9, 2014.
27.
Section 36 of
the Fisheries Act contains
the pollution prevention provisions of the Act including 36(3), which prohibits
the deposit of deleterious substances into waters frequented by fish unless
otherwise authorized.
28.
Mackenzie
Valley Land and Water
Board, Staff Report related to Dyke A Construction and
Management Plan, October 16, 2014.
29.
Mackenzie
Valley Land and Water Board,
Staff Report related to Dyke A Construction and
Management Plan, October 16, 2014.
30.
Government of
the Northwest Territories,
Environment and Natural Resources, Letter from GNWT–ENR to MVLWB re: Dyke
Construction and Management Plan, May 7, 2015.
31.
Government of
the Northwest Territories, Environment
and Natural Resources, Letter from GNWT–ENR to MVLWB re: Dyke Construction and
Management Plan, May 7, 2015.
32.
Mackenzie
Valley Land and Water
Board, Staff Report related to Dyke Construction and
Management Plan, Dykes A1, F, G, H, I, J, K, and L, May 20, 2015.
33.
De Beers
Canada Inc., Dyke
Construction Management Plan (Dykes A1, F, G, H, I, J, K, L) (March 2015).
34.
Shortly
following the discussions in 2014 and
2015, the fish-out of Kennady Lake was completed and
mine operations began in 2016. As such, there were no further construction
activities that required additional discussions on these matters. Additional
discussion between parties regarding sequencing of authorizations and whether
an area authorized for destruction under the Fisheries Act is
exempt from other relevant legislation prior to and during construction would
have been beneficial to all parties. As well, further discussions could have
addressed the applicability of various conditions of the water licence to these areas and whether mitigations were
required at different project phases.
35. Mackenzie
Valley Land and Water Board
and Aboriginal Affairs and Northern Development Canada, Guidelines for the
Closure and Reclamation of Advanced Mineral Exploration and Mine Sites in the
Northwest Territories (November 2013), https://www.lands.gov.nt.ca/sites/lands/files/resources/2013_mvlwb-aandc_guidelines_for_closure_and_reclamation.pdf.
36. Mackenzie Valley Environmental Impact Review Board Gahcho Kué Panel, Report of Environmental Impact Review and Reasons for Decision, EIR 0607-001, Gahcho Kué Diamond Mine Project (Yellowknife: July 19, 2013), https://reviewboard.ca/upload/project_document/EIR0607-001_Gahcho_Kue_Diamond_Mine_Project_Report_of_EIR.PDF.
37.
De Beers
Canada Inc., Gahcho
Kué Mine, 2020 Updated Project Description, completed
February 2020 in support of Type “A” Water Licence
amendment application, http://registry.mvlwb.ca/Documents/MV2005L2-0015/MV2005C0032%20-%20MV2005L2-0015%20-%20De%20Beers%20Gahcho%20Kue%20-%20Amendment%20Applications%20-%20Att%201%20Updated%20Project%20Description%20-%20Mar%206_20.pdf.
38.
De Beers
Canada Inc., Gahcho Kué
Closure Workshop: Interim Closure and Reclamation Plan, Record of Meeting,
March 2, 2016; Mackenzie Valley Land and Water Board, Letter to De Beers Canada
Inc. regarding Interim Closure and Reclamation Plan v.4.0, November 7, 2018.
39.
Mackenzie
Valley Land and Water Board,
Letter to De Beers Canada Inc. regarding Interim Closure and Reclamation Plan
v.4.0 November 7, 2018.
40.
Mackenzie
Valley Land and Water Board,
Letter to De Beers Canada Inc. regarding Interim Closure and Reclamation Plan
v.4.0 November 7, 2018.
41.
Canada,
Fisheries and Oceans Canada, Fisheries Act
Authorization 03-HCAA-CA6-00057, issued to De Beers Canada Inc., June 30, 2014.
42.
Government of
the Northwest Territories, Environment
and Natural Resources, Letter from GNWT-ENR to MVLWB re: Gahcho
Kué Interim Closure and Reclamation Plan, v.4.0,
August 7, 2018.
43.
De Beers
Canada Inc., Gahcho Kué Project
Environmental Impact Statement, Section 8: Key Line of Inquiry: Water Quality
and Fish in Kennady Lake, December 2010.
44.
De Beers
Canada Inc., Gahcho Kué Project
Environmental Impact Statement, Section 8: Key Line of Inquiry: Water Quality
and Fish in Kennady Lake, December 2010, 8-454 &
8-455.
45.
Government of
the Northwest Territories, Environment
and Natural Resources, Letter from GNWT-ENR to MVLWB re: Gahcho
Kué Interim Closure and Reclamation Plan, v.4.0,
August 7, 2018.
46.
Mackenzie
Valley Land and Water Board,
Letter to De Beers Canada Inc. regarding Interim Closure and Reclamation Plan
v.4.0, November 7, 2018.
47.
Mackenzie
Valley Land and Water
Board, Letter to De Beers Canada Inc. regarding Interim Closure and Reclamation
Plan v.4.0, November 7, 2018, 7.
48.
Mackenzie
Valley Land and Water Board, Letter to
De Beers Canada Inc. regarding Interim Closure and Reclamation Plan v.4.0,
November 7, 2018.
49.
Mackenzie
Valley Land and Water
Board, Letter to De Beers Canada Inc. regarding Interim Closure and Reclamation
Plan v.4.0, November 7, 2018, 7–8.
50.
Mackenzie
Valley Land and Water
Board, Letter to De Beers Canada Inc. regarding Interim Closure and Reclamation
Plan v.4.0, November 7, 2018, 8.
51.
Mackenzie
Valley Land and Water
Board, Letter to De Beers Canada Inc. regarding Interim Closure and Reclamation
Plan v.4.0, November 7, 2018, 8–9.
52.
Mackenzie
Valley Land and Water Board,
Letter to De Beers Canada Inc. regarding Interim Closure and Reclamation Plan
v.4.0, November 7, 2018.
53.
Wek’èezhìi Land and Water Board,
Reasons for Decision on BHP Billiton’s 2008 Interim Closure and Reclamation
Plan, December 10, 2010, 4.
54.
The Long Lake
Containment Facility is
an area at the Ekati mine site, formerly aquatic
habitat, that is used to manage processed kimberlite and wastewater.
55.
BHP Billiton
Diamond Inc., Letter to the
Wek’èezhii Land and Water Board re: Originating
Notice Regarding Closure and Reclamation of Pit Lakes, September 4, 2009.
56.
BHP Billiton
Diamonds Inc. v. Wek’èezhii Land and Water Board, 2010 NWTSC 23.
57.
Wek’èezhìi Land and Water Board,
Reasons for Decision on BHP Billiton’s 2009 Request for Ruling, July 26, 2009,
13
58.
Wek’èezhìi Land and Water Board,
Reasons for Decision on BHP Billiton’s 2009 Request for Ruling, July 26, 2009,
12
59.
BHP
Billiton Diamonds Inc. v. Wek’èezhii
Land
and Water Board, 2010 NWTSC
23.
60.
McCarthy Tetrault, “BHP Billiton Diamonds Inc. v. Wek’èezhii
Land and Water Board, 2010 NWTSC
23,” Mining in the Courts 2010 Year in Review, April 25, 2011, https://www.mccarthy.ca/en/insights/articles/mining-courts-2010-year-review.
61.
BHP Billiton
Diamonds Inc. v. Wek’èezhii Land and Water Board,
2010 NWTSC 23, 6.
62.
Government of
the Northwest Territories,
Environment and Natural Resources, Letter from GNWT–ENR to MVLWB re Dyke A
Construction and Management Plan, October 9, 2014; Government of the Northwest
Territories, Environment and Natural Resources, Letter from GNWT–ENR to MVLWB
re: Dyke Construction and Management Plan, May 7, 2015.
63.
Mackenzie Valley
Land and Water Board, Letter to De
Beers Canada Inc. regarding Interim Closure and Reclamation Plan v.4.0,
November 7, 2018.
64.
Mackenzie
Valley Land and Water
Board, Letter to De Beers Canada Inc. regarding Interim Closure and Reclamation
Plan v.4.0, November 7, 2018.
65.
Hill et al.,
“Harmonization versus
Subsidiarity.”
66.
P. Muldoon,
A. Lucas, R.B. Gibson, P. Pickfield, and J. Williams, An Introduction to Environmental Law and Policy in Canada
(Toronto, ON: Emond Montgomery, 2015).
67.
BHP
Billiton Diamonds Inc. v. Wek’èezhii
Land
and Water Board, 2010
NWTSC 23, 13.
68.
Hill et al.,
“Harmonization versus
Subsidiarity,” 317.
69.
D. Gibson,
“Constitutional Jurisdiction over
Environmental Management in Canada,” University of
Toronto Law Journal 23, no. 1 (1973):
54–87, 76, https://doi.org/10.2307/825276.
70.
Hill et al.,
“Harmonization versus
Subsidiarity,” 317.
71.
See http://www.archives.gov.on.ca/en/e_records/walkerton/index.html.
One of the many recommendations related to the Walkterton
Inquiry following water contamination of drinking water was that additional
communication at different levels of government may have prevented the end result. As such, it was recommended that additional
dialogue between the levels of government to clarify roles and communication
mechanisms was warranted.
72.
The Hon.
Dennis O’Connor, “Chapter 15. First Nations,” Report of the Walkerton Commission of Inquiry: A Strategy
for Safe Drinking Water, Part 2 (Toronto,
ON: Publications Ontario, 2002), https://qspace.library.queensu.ca/bitstream/handle/1974/8481/WalkertonInquiryFinalReport-Part2.pdf?sequence=2&isAllowed=y.
73.
Hill et al.,
“Harmonization versus Subsidiarity.”
74.
G. Skogstad, “Intergovernmental Relations
and the Politics of Environmental Protection in Canada,” in Federalism and the Environment: Environmental policymaking
in Australia, Canada and the United States,
eds. Kenneth M. Holland, F.L. Morton, and Brian Galligan (Westport, Conn:
Greenwood Press, 1996), 127.
75.
W.T. Gormley,
“Intergovernmental Conflict on
Environmental Policy: The Attitudinal Connection,” Political Research Quarterly 40, no. 2
(1987): 285–303.
76.
Gibson,
“Constitutional Jurisdiction
over Environmental Management.”
77.
BHP Billiton
Diamonds Inc. v. Wek’èezhii Land and Water Board, 2010 NWTSC
23, 7.
Acknowledgements
I
would like to thank the Government of the Northwest Territories Department of
Environment and Natural Resources, specifically Nathen Richea
and Robert Jenkins, for supporting my graduate studies with Royal Roads
University. As well, Douglas Sauer and GNWT Geomatics Services for providing
maps. I would also like to thank Peter Cott, Sarah
Elsasser, Amanda Park and Nathen Richea for providing
feedback and input on various drafts—their feedback was very helpful and
resulted in a much better final product. Finally, I would like to thank Deanna
McLeod at the Northern Review for
all her support in finalizing this article—thanks so much for all her feedback
and patience!